WORK ACTIVITIES

1.
2.
3.
4.
5.Loading / Unloading Boom Lift

Hazards Present

  • Plant and Equipment – impact / crushing injuries
  • Weather
  • Services (overhead)
  • Electricity (overhead power lines)
  • Hazardous equipment
  • Flying objects / debris
  • Slips, trips and falls

Risk Control Measures

  • Load/unload the boom lift on level, stable ground;
  • Check weather forecast and conditions for work area before loading/unloading, always exercise caution during inclement weather;
  • Make sure recommended distances from power lines are maintained when loading and unloading plant;
  • Make sure boom lift is centered on the vehicle and secured with the appropriate number of chains or ratchet straps as determined by relevant authority before transporting anywhere;
  • Use ramps to load and unload the boom lift;
  • Make sure the metal pins attached to the ramps are engaged and locked in place;
  • Make sure all personnel are clear of the loading ramp ‘swing arc’ area when the ramps are being lowered or raised, or when the ramps are raised and not secured;
  • When using wheel chocks, use only chocks which are contoured to the tire diameter; and
  • When winching, DO NOT place square or rectangular blocks made from timber, composite or steel etc. in front of or behind the wheels of the equipment being winched – The force applied to the corners of each block can cause the blocks to explosively eject and become potentially lethal projectiles.
  • Never use ramps to enter or exit the vehicle or trailer when on foot;
  • Provide adequate cover or protection to surfaces likely to be damaged by boom lift traffic;
  • Set out witches hats to provide a safe distance for the public to travel around the vehicle; and
  • Use the ladders or steps to enter and exit vehicle or trailer when on foot.
6.
7.

Hazards Present

  • Plant and Equipment – impact / crushing injuries
  • Weather
  • Services (overhead)
  • Electricity (overhead power lines)
  • Hazardous equipment
  • Flying objects / debris
  • Slips, trips and falls

Risk Control Measures

  • Load/unload the boom lift on level, stable ground;
  • Check weather forecast and conditions for work area before loading/unloading, always exercise caution during inclement weather;
  • Make sure recommended distances from power lines are maintained when loading and unloading plant;
  • Make sure boom lift is centered on the vehicle and secured with the appropriate number of chains or ratchet straps as determined by relevant authority before transporting anywhere;
  • Use ramps to load and unload the boom lift;
  • Make sure the metal pins attached to the ramps are engaged and locked in place;
  • Make sure all personnel are clear of the loading ramp ‘swing arc’ area when the ramps are being lowered or raised, or when the ramps are raised and not secured;
  • When using wheel chocks, use only chocks which are contoured to the tire diameter; and
  • When winching, DO NOT place square or rectangular blocks made from timber, composite or steel etc. in front of or behind the wheels of the equipment being winched – The force applied to the corners of each block can cause the blocks to explosively eject and become potentially lethal projectiles.
  • Never use ramps to enter or exit the vehicle or trailer when on foot;
  • Provide adequate cover or protection to surfaces likely to be damaged by boom lift traffic;
  • Set out witches hats to provide a safe distance for the public to travel around the vehicle; and
  • Use the ladders or steps to enter and exit vehicle or trailer when on foot.

Order with confidence

As Australia's leading SWMS provider, we guarantee your SWMS to be legally compliant and job ready.

Instant download

Industry leading simple and easy SWMS documents. Simply find the document you need, complete the checkout and have the documents instantly.

Work activities & risks

We have hundreds of pre-filled SWMS with work activities and risks for instant download. Use our self-serve download if you know which document you need or contact a specialist to build a complete compliancy package.

Australian support

Need help? Please call our dedicated support number to speak with a SWMS specialist. If outside of business hours, please use our contact form.

Word & PDF documents

Each SWMS is delivered instantly to your email in both the customised PDF and original MS Word format to allow the flexibility of any changes.

Customised logo

Look professional by having your company's logo shown. Simply upload your logo in the checkout process to complete the customisation.

What you’ll need

Having helped thousands of businesses, we've made getting compliant extremely easy.

Know which SWMS you need

Our growing self-serve SWMS library is designed to help businesses build compliance quickly.

Your business name

We connect with ABR.gov.au to help make it easier to fill out your business information.

Your logo to upload

Add your logo to the SWMS documents and look professional.

Easy to follow instructions

Our documents are designed to be easy to use. Here's a preview of just how simply it is.

See what our customers say

Helping Australian businesses solve WHS compliance quickly and easily.

24 Oct, 2018
shanep415
Awesome to deal with. Very helpful and great value for money.
24 Oct, 2018
shanep415
Awesome to deal with. Very helpful and great value for money.
24 Oct, 2018
shanep415
Awesome to deal with. Very helpful and great value for money.
Previous
Next

Need help?

If your SWMS requires special conditions as part of a tender, you need our Full Compliance Solutions See our Full Compliance

Our SWMS are used on these Tier-1 sites

Instant quote

Fill out your information

Instant quote

Elevated Work Platform (Boom Lift) SWMS

Download this customised SWMS document in 5 minutes.